In order to complete a large job, $1000$ workers were hired, just enough to complete the job on schedule. All the workers stayed on the job while the first quarter of the work was done, so the first quarter of the work was completed on schedule. Then $100$ workers were laid off, so the second quarter of the work was completed behind schedule. Then an additional $100$ workers were laid off, so the third quarter of the work was completed still further behind schedule. Given that all workers work at the same rate, what is the minimum number of additional workers, beyond the $800$ workers still on the job at the end of the third quarter, that must be hired after three-quarters of the work has been completed so that the entire project can be completed on schedule or before?
考场第一眼 / First look
把总计划时间设为单位,按每一阶段的工人数计算耗时。